East Lismore Sewage Treatment Plant

100
kW
Project Overview
-
Client
Lismore City Council -
Project
East Lismore Sewage Treatment Plant -
Project Location
Monaltrie, NSW -
Solar System Type
Grid Connected - Floating Solar -
Solar System Size
100kW -
Project Installed
January, 2018
System Overview
-
PV Modules
280 x Trina Honey Plus 355W Mono -
Panel Warranties
10 years product -
25 years performance
-
Inverter/s
2 x TRIO-50.0-TL-OUTD -
Inverter Warranty
12 years -
Install & Design
CEC-accredited, 5 year warranty on workmanship and materials
System Performance
-
Expected Energy Yield
169,669 kWh/year
Financial Performance
-
Average Savings
$24,000 per annum -
Expected Payback Period
12 years
Environmental Benefits
-
Greenhouse Gas (CO2) Reduction
168 tonnes per annum